Stormwater Drainage and Landscaping Works in Riga

21/05/2022

As part of this project, stormwater drainage and infiltration networks were installed to a depth of up to 6 meters.

The total length of the installed networks is 580 meters.

Twenty-five manholes were installed, and a stormwater pumping station was built at a depth of 8.5 meters, from which water is discharged into the city's sewerage system.

Additionally, ACO stormwater collection channels were installed.

Landscaping works included the construction of sidewalks, installation of two-level railings, and the laying of paving stones for driveways.